Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the breadcrumb-navxt domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/wp-includes/functions.php on line 6114
Middy’s – Oakleigh - George Rydell

CLIENT: Middy’s

LOCATION: Oakleigh

PROJECT

George Rydell was engaged for the construction of Middy’s latest development which was set on a prominent corner of Dandenong Road in Oakleigh.

DETAILS

George Rydell were engaged to firstly demolish the existing building and undertake an extensive clean up of the ground conditions.

Building commenced with the concrete panel construction of three retail/warehouse tenancies of approximately 750 Sq m each.

Tenancy 1 was purpose built for Middy’s while another corporate giant ‘Repco’ took up residence in Tenancy 3. In addition to the building structures, all three tenancies have a front customer car park, rear staff carpark and delivery bays.